Model Table PROJECT ACTIVITY INFORMATION

Attributes

Attribute Description (where applicable)
Activity Seq KeyRepresents the Activity Sequence Key of the fact
Control Category KeyRepresents the Control Category Key

Measures (table to be generated as far as possible)

Aggregation of measures is based on SUM if not explicitly noted.

This section describes the basic measures in the cube. These are either measures defined in the core Information Source, in the model itself or in the ETL process. The columns have the following meaning:

Measure Calculated Y/N Contains Time Intelligence Y/N Definition/Note (where applicable) Aggregation Type Hidden Y/N Tabular Expression
Actual CostNNNSUM('PROJECT ACTIVITY INFORMATION'[ACTUAL])
Actual HoursNNNSUM('PROJECT ACTIVITY INFORMATION'[ACTUAL_HOURS])
Actual RevNNNSUM('PROJECT ACTIVITY INFORMATION'[ACTUAL_REVENUE])
Baseline CostNNNSUM('PROJECT ACTIVITY INFORMATION'[BASELINE])
Baseline HoursNNNSUM('PROJECT ACTIVITY INFORMATION'[BASELINE_HOURS])
Committed CostNNNSUM('PROJECT ACTIVITY INFORMATION'[COMMITTED])
Committed HoursNNNSUM('PROJECT ACTIVITY INFORMATION'[COMMITTED_HOURS])
Earned Value CostNNNSUM('PROJECT ACTIVITY INFORMATION'[EARNED_VALUE])
Earned Value Cost Progress BasisNNYSUM('PROJECT ACTIVITY INFORMATION'[EARNED_VALUE_COST_EXCLUDE_WAD])
Earned Value HoursNNNSUM('PROJECT ACTIVITY INFORMATION'[EARNED_VALUE_HOURS])
Earned Value Hours Progress BasisNNYSUM('PROJECT ACTIVITY INFORMATION'[EARNED_VALUE_HOURS_EXCLUDE_WAD])
Estimated RevNNNSUM('PROJECT ACTIVITY INFORMATION'[ESTIMATED_REVENUE])
Estimated CostNNNSUM('PROJECT ACTIVITY INFORMATION'[ESTIMATED])
Estimated HoursNNNSUM('PROJECT ACTIVITY INFORMATION'[ESTIMATED_HOURS])
Planned Committed CostNNNSUM('PROJECT ACTIVITY INFORMATION'[PLANNED_COMMITTED])
Planned Committed HoursNNNSUM('PROJECT ACTIVITY INFORMATION'[PLANNED_COMMITTED_HOURS])
Planned CostNNNSUM('PROJECT ACTIVITY INFORMATION'[PLANNED])
Planned Cost Progress BasisNNYSUM('PROJECT ACTIVITY INFORMATION'[PLANNED_COST_EXCLUDE_FROM_WAD])
Planned Cost Progress Basis RCNYReporting Currency calculationYSUM('PROJECT ACTIVITY INFORMATION'[REP_CURR_PLANNED_COST_EXCLUDE_FROM_WAD])
Planned HoursNNNSUM('PROJECT ACTIVITY INFORMATION'[PLANNED_HOURS])
Planned Hours Progress BasisNNYSUM('PROJECT ACTIVITY INFORMATION'[PLANNED_HOURS_EXCLUDE_FROM_WAD])
Planned RevNNNSUM('PROJECT ACTIVITY INFORMATION'[PLANNED_REVENUE])
Posted RevNNNSUM('PROJECT ACTIVITY INFORMATION'[POSTED_REVENUE])
Preliminary RevNNNSUM('PROJECT ACTIVITY INFORMATION'[PRELIMINARY_REVENUE])
Scheduled Work CostNNNSUM('PROJECT ACTIVITY INFORMATION'[SCHEDULED_WORK])
Scheduled Work HoursNNNSUM('PROJECT ACTIVITY INFORMATION'[SCHEDULED_WORK_HOURS])
Used CostNNNSUM('PROJECT ACTIVITY INFORMATION'[USED])
Cost Progress %YNN IF([Planned Cost Progress Basis] > 0 , [Earned Value Cost Progress Basis]/[Planned Cost Progress Basis], BLANK())
Earned Value Cost Progress Basis RCNYReporting Currency calculationN SUM([REP_CURR_EARNED_VALUE_COST_EXCLUDE_FROM_WAD])
Cost Progress % RCYYReporting Currency calculationN IF([Planned Cost Progress Basis RC] > 0 , [Earned Value Cost Progress Basis RC]/[Planned Cost Progress Basis RC], BLANK())
Hours Progress %YNN IF([Planned Hours Progress Basis] > 0 , [Earned Value Hours Progress Basis]/[Planned Hours Progress Basis], BLANK())
Project MarginYNN [Actual Rev]-[Actual Cost]
Project Margin %YNN IF([Actual Rev] > 0 , [Project Margin]/[Actual Rev], BLANK())

Time Intelligence Measures

Time based measures are calculated in the cube with respect to other measures. The table below defines the meaning/definition of  the different time measures. These measures need to be used with a specific time dimension hierarchy [REPORTING_DATE].[RepDateMFHy].

Measure Meaning
Ytd Aggregated value for current month in current  year. E.g. for period 201210 Ytd represents sum of periods 201200-201210.
R12 For a given period, the sum all months from one year back up to the previous month. E.g. Rolling 12 for 201210 is the sum of months 201110 - 201209
PY Previous Year
The value of the corresponding month one year back. E.g. for month 201210, the value of month 201110.
YTD PY Year to Date Previous Year
Aggregated value for corresponding month one year back. E.g. for month 201210 YTD Previous Year represents sum of months 201101-201110.
R12 PY Rolling 12 (completed) Months Previous Year
For a given month, first going one year back, then taking the sum of all months from one (more) year back up to the previous month. E.g. for month 201210 the sum of month 201010-201109
Avg XXX Ytd Sum XXX YTD/Count XXX YTD
Avg XXX R12 Sum XXX R12/Count XXX R12
XXX % YTD Count XXX YTD/Count YYY YTD
XXX % R12 Count XXX R12/Count XXX R12

USED BY MODEL(S)

Model Name Product Area

Data source Information

The data source for this object is defined using IFS Developer Tool. The data source contains a number of transformations where the model reads data from the last step, i.e. the Data source view name (DW Source View Name).

Link to information source documentation: . http://blablabla to be generated...

Model Table DW Source view (SQL Server) BI Access View Referenced Information Source Recommended Access Type
PROJECT ACTIVITY INFORMATIONFACT_PROJ_ACTIVITY_INFO_TMFACT_PROJ_ACTIVITY_INFO_BIFACT_PROJ_ACTIVITY_INFOOn Line

SPECIAL INFO